Project page

Ntui Solar Photovoltaic Power Plant

250 MWdc installed, 200 MWac injected, with battery storage - Centre Region, Cameroon

Early-stage development - pre-feasibility complete Position as at 28 September 2026 - financial model V4.4 parameters

A utility-scale solar project developed under a public-private partnership with the Conseil Régional du Centre, in consortium with TES Technologies SARL, our strategic and technical partner in Cameroon.

Our role and our partners' roles

WB Synergy SAS

Co-sponsor. Project structuring, financial modelling, bankability preparation, coordination of studies and engagement with development finance institutions.

TES Technologies SARL

Strategic and technical partner in Cameroon. A Cameroonian company active in high-standard electricity infrastructure projects and technology integration. Local anchoring, technical and operational interface.

Conseil Régional du Centre

Contracting public authority, within Cameroon's decentralisation framework. Public party to the partnership.

Project characteristics

Data from the Conceptual Summary V3.0 of 8 July 2026, which supersedes version V2.0 of 30 March 2025 in its entirety.
LocationNtui municipality, Mbam-et-Kim division, Centre Region, Cameroon
Injected capacity200 MWac at the connection point - reading to be confirmed in the connection agreement
Installed capacity250 MWdc of modules, a direct-to-alternating current ratio of 1.25
Storage60 MW / 120 MWh, two hours of discharge - supporting the evening peak and system stability
TechnologyFixed-tilt structures on driven piles. The single-axis trackers specified until August 2026 were dropped: at this level of irradiation they justified neither their capital cost nor thirty years of maintenance.
Reference production328,400 MWh in year 1 (P50, 80% performance ratio), or 1,314 kWh/kWp - sponsor estimate, to be confirmed by the independent yield study
Envisaged connection225 kV substation and evacuation line to the Southern Interconnected Grid; approximately 30 km carried in the model, route and injection limit to be confirmed with SONATREL
Land footprintApproximately 600 to 664 hectares, to be confirmed by land and cadastral surveys and by the impact assessment
Indicative scheduleFinancial close 2027, 24 months of construction, commissioning 2029, 30 years of operation
OfftakerTo be finalised. Anticipated counterparty: SOCADEL, subject to confirmation. No power purchase agreement is signed to date.
StructurePublic-private partnership with the Centre Regional Council
StageEarly-stage development - pre-feasibility completed
The Ntui site in its landscape Map: the Ntui site in its local setting of wooded savanna and gallery forest along the Sanaga corridor, showing the indicative project area. Sanaga to Yaoundé Ntui Planned 225/30 kV substation (location indicative) Indicative project area not secured land Nachtigal hydropower plant (420 MW) N Schematic - not to scale Wooded savanna Gallery forest Sanaga Indicative project area Planned 225/30 kV substation Road Built-up area
Wooded savanna with gallery forest along the watercourses - a forest-savanna mosaic (rainfall 1,200-1,600 mm/yr, December-February dry season). The project area shown is indicative; no land is secured. Interim working map, not to scale.

What the selected scenario assumes

Financial model V4.4 is explicitly conditional. Three items, none of them yet secured, carry the selected scenario: without them the project does not finance in its present form. We publish them because a project whose conditions are unknown is not a project anyone has assessed.

What the selected scenario assumes
Condition Nature and status
Ten-year corporate income tax exemption Under Law No. 2013/004 on private investment incentives, within an investment convention. The application has still to be filed; no decision has been obtained.
Administrative decision - not granted
Operations and maintenance contract with capped escalation Contractual escalation limited to 3% per year on the largest operating cost line. At this stage this is an assumption: no contract is signed.
Commercial contract - to be negotiated
Injected capacity read at 200 MWac The injection limit at the connection point, for 250 MWdc installed upstream. Put to ARSEL and SONATREL; it will have to be settled in the connection agreement.
Regulatory and technical confirmation - to be confirmed

These three are not of the same kind. The third is a matter for the regulator and the grid operator, and was put to ARSEL at the working session of 8 September 2026; the first is a separate administrative decision and the second a commercial negotiation. No administration consulted has pronounced on their outcome, and we attribute no view to any of them here.

Institutional dialogue under way

By correspondence of 27 August 2026, the Electricity Sector Regulatory Agency invited the consortium to a working session, held on 8 September 2026 and chaired by its Director General. The project was presented there across its technical, economic, financial, regulatory and environmental dimensions, including the elements not yet established. The questions submitted concerned the applicable title regime, the composition of the file, the reading of injected capacity, connection conditions, justification of the purchase price, indexation and the valuation of the storage service. The guidance received is being incorporated. In the days that followed, first-contact letters were addressed to the Ministry of Water and Energy, to the Ministry of the Economy, Planning and Regional Development and to SONATREL, and an amendment letter to SOCADEL.

These are approaches and consultations. They carry no authorisation, no approval and no commitment from any of the entities named.

Milestones achieved and next steps

Ntui project - milestones and next steps Timeline: milestones achieved on the Ntui project from 2024 to September 2026, followed by the next steps, which are not yet achieved. Achieved Next steps - no dates committed Memorandum ofunderstanding 2024 Initial conceptnote 2024 Conceptualdocument 30 Mar 2025 ConceptualSummary V3.0 8 Jul 2026 Financial Model V4.4,ARSEL working session Sep 2026 Independent yield study Land control and easements Full ESIA to IFC standards Grid studies with SONATREL PPA term sheet Competitive EPC tender Forward items are shown in sequence only; durations will follow the studies.
Milestones achieved from 2024 to September 2026; next steps in sequence, with no completion dates committed. The full list is set out below. Interim working diagram.

Milestones achieved

  • Achieved Memorandum of understanding signed between the Conseil Régional du Centre and the TES Technologies - WB Synergy consortium
  • 2024 Initial project concept note
  • 30 March 2025 Conceptual document issued to the Conseil Régional du Centre
  • 8 July 2026 Conceptual Summary V3.0 - full rebuild of technical, financial and market content
  • July 2026 Financial Model V2.2 and bankability memorandum
  • 8 September 2026 Working session at ARSEL, at the Agency's invitation
  • 9 September 2026 Financial model V4.4 - reconfigured to 250 MWdc / 200 MWac with storage doubled
  • September 2026 First-contact letters to MINEE, MINEPAT and SONATREL; amendment letter to SOCADEL

Next steps

  • Next step Independent P50/P90 yield study and on-site measurement campaign
  • To commence Land control: surveys, titles and easements
  • To commence Full environmental and social impact assessment to IFC Performance Standards
  • To commence Grid-connection studies and agreement with SONATREL
  • To commence Power purchase agreement term sheet with the offtaker
  • To commence Competitive EPC tender and capital cost validation

Why this site

The site lies immediately adjacent to the planned 225/30 kV Ntui substation, part of the RIS-RIN interconnection project - a double-circuit 225 kV backbone of approximately 530 km linking the Southern and Northern interconnected grids, scheduled over 2023-2027. The line is financed by the World Bank (IDA); the four 225/30 kV substations, Ntui among them, are financed by the Islamic Development Bank. That proximity is the project's principal grid-integration argument. The connection point, voltage level and permitted export capacity must be confirmed through connection studies and an agreement with SONATREL.

Cameroon power sector context

National installed capacity stood at 2,011 MW in 2025, of which roughly 70% hydropower - output exposed to dry-season low flows. Solar accounts for only about 3% of installed capacity. Commissioning of the Nachtigal hydropower plant (420 MW) over 2024-2025 increased national capacity by around 30%, without removing the seasonality of the resource or transmission constraints. A solar project with storage provides complementary daytime energy, reduces reliance on thermal generation and supports grid stability.

Sources: data presented by the Ministry of Water and Energy, November 2025; World Bank, January 2025.

The RIS-RIN interconnection and the Ntui node Diagram: the 225 kilovolt RIS-RIN interconnection between Cameroon's southern and northern grids, with the planned Ntui substation as the southern interconnection node. RIS Southern Interconnected Grid RIN Northern Interconnected Grid Double-circuit 225 kV approx. 514-531 km Nachtigal hydropower plant 420 MW · commissioned 2025 Ntui 225/30 kV · RIS interconnection node Yoko 225/30 kV Tibati 225/30 kV Hourou Oussoa 225/30 kV (near Ngaoundéré) Proposed Ntui solar plant 250 MWdc · early-stage development Connection subject to studies and an agreement with SONATREL N Line: World Bank (IDA), US$266m · Four 225/30 kV substations: Islamic Development Bank Schematic - not to scale
The RIS-RIN interconnection: double-circuit 225 kV, approx. 514-531 km, from Nachtigal to Hourou Oussoa, with four 225/30 kV substations (Ntui, Yoko, Tibati, Hourou Oussoa). Ntui is the planned RIS interconnection node. Line financed by the World Bank (IDA); substations by the Islamic Development Bank. Interim working diagram, not to scale.

Environmental impact - method and limitations

On the basis of net production of 328,400 MWh in year 1 and an average Cameroonian grid emission factor of 0.2259 tCO₂e/MWh (lifecycle carbon intensity; Ember / Our World in Data, 2024), avoided emissions are estimated at approximately 74,200 tCO₂e for the first year of operation.

Method. Method: avoided emissions = net electricity exported × grid emission factor. Factor used: average carbon intensity of Cameroon's electricity grid, 2024 data (Ember, via Our World in Data, 2025 release).

Limitation. Methodological limitation: this grid-average factor, pulled down by the hydro-dominated mix, is conservative. A combined-margin factor established under the UNFCCC Tool07 methodology would likely give a higher result. This estimate is indicative and will be updated during the environmental and social impact assessment.

Integrity note. Earlier versions of this project's documentation cited an avoided-emissions figure of 131,400 tCO₂ per year, together with cumulative return-on-investment and break-even indicators. These are not carried over: they are expressly superseded by the Conceptual Summary V3.0 of 8 July 2026, which is the sole document in force.


The information on this page is provided for general information only and constitutes neither an offer, nor a solicitation, nor a contractual commitment. The project's financial data are confidential and are not published. The project is in development: its realisation remains subject to obtaining permits, securing land, concluding contracts and reaching financial close.

Discuss a project